Pickens Hall Construction

Pickens Hall Updates as of August18, 2026

Flooring installation on the second floor is underway, along with painting throughout the building. Installation of wall graphics has also begun. The elevator installation is complete, and the building’s systems are now operational. Installation of the precast concrete treads for the monumental stair has begun. Upcoming work includes completing the exterior slab-on-grade and interior polished concrete finish work. Landscaping will begin once all concrete has been poured.

Classroom on the second floor of Pickens Hall

Classroom on the second floor

Example of second floor huddle space in Pickens Hall

Example of second floor huddle space

Monumental Stair pre-cast tread installation has begun in Pickens Hall

Monumental Stair pre-cast tread installation has begun

Painting and finishes ongoing in Pickens Hall

Painting and finishes ongoing

Pickens Hall flooring in the second floor business lounge. Amazing views to the north.

Flooring in the second floor business lounge. Amazing views to the north.

Bathroom finishes underway in Pickens Hall

Bathroom finishes underway

Front Drive Lobby lighting baffles in Pickens Hall

Front Drive Lobby lighting baffles

Pickens Hall Updates as of July 9, 2026

Pickens Hall continues to make steady progress toward completion. Exterior building signage has been installed, and exterior concrete footings are being constructed. Work on the emergency drive aisle will begin soon.

Inside the building, first-floor ceiling tiles are in place and second-floor lighting has been installed. Final finishes are ongoing on the first floor as the project moves closer to completion.

Pickens Hall exterior signage installed

Exterior signage installed

PH longboard ceiling nearly complete in the main lobby

Longboard ceiling nearly complete in the main lobby

PH 2nd floor lighting has been installed

Pickens Hall 2nd floor lighting has been installed

PH Faculty Neighborhood carpeting has begun

Faculty Neighborhood carpeting has begun

PH Millwork installation in the Faculty Lounge

Millwork installation in the Faculty Lounge

Pickens Hall view from the future business lounge

Pickens Hall stunning view from the future business lounge

Pickens Hall updates as of June 4, 2026

Interior longboard ceiling installation has begun in the main lobby. First-floor restroom tile has been installed. First-floor lighting has been installed and is operational. Storefront systems have been installed in the Dean's Suite and Faculty Neighborhood.

During June, first-floor ceiling tile installation and cabinetry installation will begin. Work will also continue on the second floor with installation of the ceiling grid, electrical lighting and devices, as well as tile installation in the second-floor restrooms.

Tile being installed in the restroom

Tile installation in the restroom

Pickens Hall Dean's suite storefronts

Dean's Suite Storefronts

Pickens Hall updates as of May 21, 2026

Pickens Hall exterior with pannels installed

All ACM panels have now been installed on Pickens Hall and the building exterior has really begun to take shape. Planned occupancy for Pickens Hall is January 2027.

Pickens Hall updates as of May 15, 2026

Pickens Hall exterior panels rendering

Pickens Hall exterior panels rendering

Pickens Hall monumental stairs rendering

Monumental stair rendering

Pickens Hall monumental stairs and railing

Monumental stairs and railing installed

Pickens Hall 2nd floor main hall rendering

Pickens Hall 2nd floor main hall rendering

Pickens Hall 2nd floor main hall

Pickens Hall 2nd floor main hall

Pickens Hall updates of April 23, 2026

 

The building dry-in, along with conditioned air, has been completed. Installation of the north side ACM panels began on April 21. Drywall is nearing completion throughout the building, and both the prime coat and first coat of paint are underway. Mechanical final connections are in progress, and cable tray installation has begun, with the first data cable pulls now starting.

Pickens Hall exterior masonry complete

Exterior Masonry Complete

Pickens Hall exterior rendering

Pickens Hall exterior rendering

Faculty lounge nook

Faculty lounge nook

Faculty lounge nook rendering

Faculty lounge nook rendering

Pickens Hall 2nd floor nook

2nd floor nook

Pickens Hall 2nd floor nook rendering

2nd floor nook rendering

Pickens Hall 2nd floor grand hallway

2nd floor grand hallway

Pickens Hall 2nd floor grand hallway rendering

2nd floor grand hallway rendering

Pickens Hall updates as of March 26, 2026

Pickens Hall construction progress facing front drive

Pickens Hall facing front drive

Pickens Hall construction progress facing Project Nexus (center spine)

Pickens Hall facing Project Nexus (center spine)

New Pickens Hall Front Drive

Pickens Hall rendering of front drive

Pickens Hall front drive drop off rendering

Pickens Hall front drive drop off rendering

Pickens Hall grassy area rendering

Pickens Hall grassy area rendering

Pickens Hall from a distance rendering

Pickens Hall from a distance rendering

Pickens Hall exterior from Oconee Hall rendering

Pickens Hall exterior from Oconee Hall rendering

Pickens Hall exterior main lobby rendering

Pickens Hall exterior main lobby rendering

Pickens Hall updates as of February 26, 2026

1st Floor

  • Drywall is complete.
  • Electrical crews are pulling overhead and in-wall wiring
  • Mechanical room buildout is underway
  • Ductwork trim-out is in progress

2nd Floor

  • Drywall installation has begun.
  • Electrical overhead rough-in is in progress.
  • Hard ceiling rough in is underway at the north lobby clerestory.

Exterior

  • Masonry work on the east elevation continues
  • Glazing installation is ongoing throughout the building
Pickens Hall first floor drywall complete in the Faculty Neighborhood

First floor drywall complete in the Faculty Neighborhood

Pickens Hall main lobby drywall and glazing work

Main lobby drywall and glazing work

Pickens Hall one of two 50-person classrooms

One of two 50-person classrooms

Pickens Hall congrstructio progress August 2025 - topping out beam visible

Progress August 2025 - topping out beam visible

Pickens Hall construction progress as of February 2026

Progress as of February 2026

Pickens Hall construction front drive masonry completed

Front drive masonry completed

West side of Pickens Hall view from Oconee masonry completed

West side of Pickens Hall view from Oconee masonry completed

Pickens Hall construction masonry continues on Eastern side

Masonry continues on Eastern side

Pickens Hall construction mechanical systems installed

Mechanical systems installed

December Progress Highlights

  • Wall panel installation for televisions has begun throughout the building
  • Building sheathing and waterproofing have been successfully completed
  • Drywall installation is underway on the first floor
  • Spray foam insulation installation has started
  • Glazing (window) installation is now in progress
Pickens Hall construction drywall install begins

Drywall install begins

Pickens Hall construction window install front drive side

Window Install Front Drive Side

Pickens Hall construction wall blocking for TVs

Wall Blocking for TVs

Looking Ahead: Next 30 Days

As we move forward, the following activities are scheduled:

  • Masonry work to begin
  • Completion of the sprinkler system throughout the building
  • Drywall installation to start on the second floor
  • Plumbing and mechanical work continues on the second floor

1st floor work has included Framing, Mechanical, Electrical and Plumbing work. Lobby facing Center Spine

Pickens Hall first floor lobby
Pickens Hall first floor lobby rendering

Faculty Neighborhood and Adjunt Space

Pickens Hall faculty neighborhood and adjunt space wall structure
Faculty neighborhood and adjunct rendering

Exterior sheathing and waterproofing continues

Pickens Hall exterior facing Anderson Hall
Pickens Hall exterior front drive
Pickens Hall view from front drive rendering

2nd floor Mechanical, Electrical, Plumbing and Framing

Pickens Hall second floor corner nook space
Pickens Hall second floor corner nook space rendering
Pickens Hall second floor at monumental stair
Pickens Hall second floor at monumental stair rendering
beam to be signed by employees under a tent

Sign the Beam

Beam location for Pickens Hall

Beam location for Pickens Hall

 SIGN THE BEAM!


Be Part of New Pickens Hall History

 Behind the AHEC, facing the Center Spine
Available Now Through August 14
Convocation – 9:00 AM, August 14
Beam Raising – 10:15 AM, August 14

 

The beam is ready—stop by anytime to sign it and leave your mark on the future of New Pickens Hall!

 

Join us after Convocation on August 14 for the Topping Out Ceremony, when the signed beam will be raised into place.

Before demolition began on Pickens Hall

Before demolition began on Pickens Hall

The separation of Pickens from Anderson Hall

The separation of Pickens from Anderson Hall

Pickens Hall completely removed

Pickens Hall completely removed

Early stages of footings being poured and the outline of the new building beginning to take shape

Early stages of footings being poured and the outline of the new building beginning to take shape